The following is a statement from CUB Executive Director Sarah Moskowitz on the results of PJM Interconnection’s 2027-28 capacity auction, announced Wednesday, Dec. 17 (Read the full statement here.) After a third straight auction marked by unacceptably high prices, it is painfully obvious that our capacity market is breaking under…...
Heading into 2026, CUB names biggest threats to utility bills
Based on its experience combatting high utility costs over the past year, the consumer watchdog Citizens Utility Board (CUB) of Illinois has issued its list of what looks to be major threats to utility affordability in 2026. “As consumers struggle with high prices across the board for everyday necessities like…...
Data center distress: CUB, NRDC experts warn PJM states could get hit with forced blackouts, $163B in electricity capacity costs
Record new demand from data centers is driving up energy costs and concerns about reliable power supply. Preliminary utility forecasts in PJM Interconnection, the largest power grid operator in the country, show that data centers could require more than 50 gigawatts of peak electricity capacity by 2030 — enough to…...